BLUE RIVER BASIN (Dodson Ind. District), Kansas City, MO - FY16 $14,400,000 Construction
STATUS
• FY16 $14.4M along with FY15 $2M completes project.
• $3.8M remaining under the current authorization.
• PACR submitted for modification of project costs to $47M.
• Phases 1, 2, 3 and 4A complete.
• Remaining Phase 4 design nearly complete.
BENEFIT OF PROJECT
500-year flood protection of nearly $380,000,000 of property investment and 1,500 employees and major road connections providing safe egress during floods.