SWOPE PARK INDUSTRIAL AREA, Kansas City, MO - FY16 $10,000,000 Construction
STATUS
• FY16 $10M for major construction contract will result in overall cost savings. $2.8M minimum needed for crucial bank stabilization to prevent cost increase.
• $10M remains under current authorization.
• $16M completes the project.
• PACR submitted for modification of project costs to $30.3M.
• Interior drainage system installation completed.
• Remaining project under design.
• Bridge design underway at sponsor cost.
BENEFIT OF PROJECT
Eliminates at grade RR crossing and protects economically vital business park comprised of various lean manufacturing facilities providing over 400 skilled manufacturing jobs from up to the 0.2 percent chance (500-year) flood event.